Multi-purpose SNCB workshop

  • Location: MELLE [BE]
  • Discipline: INDUSTRY & BUILDINGS
  • Period: 2014 - 2017
  • The lattice work in the reinforcement in the floor slab in the first hall is well underway.
    2016
  • Start construction
    2014
  • Start of study
    2014
  • Polyvalente werkplaats NMBS engineering SBE #teamsbe #expertsatplay
  • Polyvalente werkplaats NMBS engineering SBE #teamsbe #expertsatplay
  • Polyvalente werkplaats NMBS engineering SBE #teamsbe #expertsatplay
  • Polyvalente werkplaats NMBS engineering SBE #teamsbe #expertsatplay

The new multi-purpose SNCB workshop in Melle replaces the Merelbeke traction workshop and the central workshop in Gentbrugge. Both sites were very outdated and not equipped to maintain the new multiple-unit trains. The new workshop was built on the old marshalling yard between the Vijverwegel and the Nonnenwegel, on the axis of the important Brussels-Coast-Antwerp railway lines.

Two large halls with workshops and accompanying buildings were erected for maintenance, repair and cleaning of trains. The works include work on the shells, finishing and equipping tasks, including track laying inside the halls.

Polyvalente werkplaats NMBS engineering SBE #teamsbe #expertsatplay

The concrete floors of both large halls required special attention. On the one hand, it was necessary that they were absolutely watertight. On the other, these monolithic plates form part of a giant area of no less than 200 metres by 200 metres. Because of these enormous dimensions, special attention had to be paid to shrinkage effects and the limitation of crack formation, especially since the trainsets to be maintained travel over this area. On the basis of its expertise and knowledge, SBE was called upon to take care of the entire design of these floors, including the layout of the plan.

In addition, SBE also investigated alternatives for the basic design of the halls, which involved the steel structure of the halls. Alternative designs were examined within a steel-concrete structure and finally found within a totally concrete structure.

Responsibilities SBE

  • Full implementation design including drawing up of reinforcement and formwork drawings of both the two large halls and the outbuildings
  • Feasibility study for the two large halls: In the feasibility study it was investigated whether other options are possible than to carry out the entire skeleton construction exclusively in steel. For this, alternative designs were investigated in a steel-concrete construction and found in a complete concrete structure

Recent projects

From Antwerp to India, SBE is taking steps in progress and innovation all over the world. Below you will find a selection of our most recent projects.

Discover all projects

Our awards

Other news

Curious about what is happening within SBE? Or in which projects we are involved? Through these newsitems we will keep you informed about our projects and the ins and outs within SBE.

Discover our scoops
Seine-Schelde sluis Harelbeke engineering SBE #teamsbe #expertsatplay

Questions?

Do not hesitate to contact us, we are happy to help you!

Contact us