NATO Leopold III Tunnel

  • Location: BRUSSELS [BE]
  • Discipline: BURGERLIJKE BOUWKUNDE & INFRASTRUCTUUR
  • Period: 2005 - 2013
  • Completion of works above ground
    January 2013
  • Initial work on the tunnel
    October 2012
  • Start of the works
    May 2010
  • Start of study
    February 2005
  • Navo Tunnel engineering SBE #teamsbe #expertsatplay
  • Navo Tunnel engineering SBE #teamsbe #expertsatplay
  • Navo Tunnel engineering SBE #teamsbe #expertsatplay
    Navo Tunnel

The construction of the new NATO headquarters along Boulevard Leopold III in Brussels also required a major infrastructural intervention: a new tunnel made it possible to smoothly steer through traffic towards the city centre. This made it possible to build an intermodal hub above ground for the traffic to this NATO-quarter, and create a connection to the public transport network.

The major infrastructure project consisted of the following sub-tasks:

  • A complete reconstruction of the Boulevard Leopold III and its parallel roads
  • Extension of tram line 55 from the current NATO car park to the regional border
  • Realisation of a 235 metre long tunnel with two lanes in both directions

These interventions improved access to the adjoining industrial sites and found a balance between the different modes of transport in the neighbourhood. In addition to cars, soft road users and public transport were also taken into consideration. This solution for the ever-increasing traffic flow therefore offers improved safety and traffic flow.

Navo Tunnel engineering SBE #teamsbe #expertsatplay

Thanks to the versatility of SBE’s core activities, this entire project could be designed from an integrated approach. There were major challenges, especially in the field of infrastructure and electromechanics. From the preliminary design to tendering, SBE provided the geotechnical (detailed) design and structural (detailed) design for the tunnels and approaches in terms of infrastructure, as well as drawing up all the formwork and reinforcement plans.

Navo Tunnel engineering SBE #teamsbe #expertsatplay

SBE also carried out a complete study of hydraulics, mechanics, electromechanics and automation. This included high and low voltage equipment, tunnel lighting, safety signs, dynamic traffic management, a redundant pumping system and the preparation of risk analyses for design and implementation. Finally, supervision of the works was also entrusted to SBE.

A total package in the heart of Brussels!

Taksks SBE

  • Complete study of hydraulics, mechanics, electromechanics and automation
  • Preliminary design
  • Site follow-up

Recent projects

From Antwerp to India, SBE is taking steps in progress and innovation all over the world. Below you will find a selection of our most recent projects.

Discover all projects

Our awards

Other news

Curious about what is happening within SBE? Or in which projects we are involved? Through these newsitems we will keep you informed about our projects and the ins and outs within SBE.

Discover our scoops
Seine-Schelde sluis Harelbeke engineering SBE #teamsbe #expertsatplay

Questions?

Do not hesitate to contact us, we are happy to help you!

Contact us